Following are the manpower requirements for each activity in a project: (a) Draw the network and find
Question:
Following are the manpower requirements for each activity in a project:
(a) Draw the network and find out total float and free float for each activity.
(b) The contractor stipulates that during the first 26 days only 4 to 5 men and during remaining days 8 to 11 men only can be made available. Rearrange the activities suitably for levelling the manpower resources, satisfying the above condition.