Following table gives the list of various activities involved in the launch of a new CREDIT CARD service by a company, their immediate predecessors and their expected durations (in days):

image text in transcribed

image text in transcribed

where T0 = most optimistic time, Tm = most likely time, and TP = most pessimistic time

(a) Draw an arrow diagram for the project.

(b) Find the expected project completion time of the project.

(c) Determine the probability of completing the project in 165 days.