Super Fun Industries manufactures four top-selling toys code named A-148, B-356, B-457, and C-843. The following table

Question:

Super Fun Industries manufactures four top-selling toys code named A-148, B-356, B-457, and C-843. The following table shows how long it takes to process each toy through each required station. Note that all times are in minutes. Super Fun's manufacturing plant is open 16 hours a day, 5 days a week, and 8 hours on Saturday.
Super Fun Industries manufactures four top-selling toys code named A-148,

a. If only toy A-148 is produced during a specific week, how many units could be produced?
b. If weekly demand for the four products are A-148 = 200 units, B-356 = 250 units, B-457 = 250 units, and C-843 = 300 units, which station is the bottleneck, and is it capable of producing all the toys demanded?

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Operations Management Processes and Supply Chains

ISBN: 978-0133872132

11th edition

Authors: Lee J. Krajewski, Manoj K. Malhotra, Larry P. Ritzman

Question Posted: