The flexible budget formula is fixed costs $50,000 plus variable costs of $4 per direct labor hour.

Question:

The flexible budget formula is fixed costs $50,000 plus variable costs of $4 per direct labor hour. What is the total budgeted cost at
(a) 9,000 hours and
(b) 12,345 hours?