The following data relate to direct labor costs for the production of smart tablets. Actual: ......... 6,300

Question:

The following data relate to direct labor costs for the production of smart tablets.

Actual: ......... 6,300 hrs. at $23.00.............. $144,900

Standard: ...... 6,300 hrs. at $24.50 .............. $147,000

a. Determine the rate variance, time variance, and total direct labor cost variance.

b. Discuss what might have caused these variances?