Using Johnson's rule for 2-machine scheduling, the Scheduled Order ____________________Job 1...................................................C 2...................................................A 3...................................................D 4...................................................B 5...................................................B 6...................................................E For
Question:
Using Johnson's rule for 2-machine scheduling, the
Scheduled Order ____________________Job
1...................................................C
2...................................................A
3...................................................D
4...................................................B
5...................................................B
6...................................................E
For the schedule developed using Johnson's rule, the total length of time taken to complete the six jobs (including the 2nd operation) = I hours (enter your response as a whole number).
Six jobs are to be processed through a two-step operation.
The first operation involves sanding, and the second involve painting. Processing times are as follows:
Step by Step Answer: