You are in charge of a project at the local community center. The center needs to remodel

Question:

You are in charge of a project at the local community center. The center needs to remodel one of the rooms in time for the start of a new program. Delays in the project mean that the center must rent other space at a nearby church at additional cost. Time and cost data for your project are contained in Table. Your interest is in minimizing the cost of the project to the community center.

You are in charge of a project at the local

a. Using the normal times for each activity, what is the earliest date you can complete the project?
b. Suppose the variable, overhead costs are $50 per day for your project. Also suppose that the center must pay$40 per day for a temporary room on day 15 or beyond. Find the maximum cost projectschedule.

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Operations management processes and supply chain

ISBN: 978-0136065760

9th edition

Authors: Lee J Krajewski, Larry P Ritzman, Manoj K Malhotra

Question Posted: