Information concerning Toomey Company's manufacturing activities for December follows: Total December manufacturing cost was $180,000, of which

Question:

Information concerning Toomey Company's manufacturing activities for December follows:
Information concerning Toomey Company's manufacturing activities for December follows:
Total Decemb

Total December manufacturing cost was $180,000, of which $30,000 was direct labor cost. A total of 600 machine hours were used in the month. The company uses a predetermined overhead rate of $100 per machine hour to assign factory overhead to work in process and finished goods inventories. Materials purchased in December were $87,000 and freight-in on these purchases totaled $ 1,500.
Required:
Compute the following:
(1) Materials used in December
(2) Work in process at December 31
(3) December cost of goods manufactured
(4) Finished goods at December 31
(5) December cost of goods sold

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Cost Accounting

ISBN: 978-0759338098

14th edition

Authors: William K. Carter

Question Posted: