Overhead information for Cran-Mar Company for October follows: Total overhead incurred.............................................$30,000 Budgeted fixed overhead.............................................$7,125 Total standard overhead
Question:
Overhead information for Cran-Mar Company for October follows:
Total overhead incurred.............................................$30,000
Budgeted fixed overhead.............................................$7,125
Total standard overhead rate per machine hour (MH).............$4.90
Standard variable overhead rate per MH............................$3.00
Standard MHs allowed for the units manufactured...............3,600
Required
1. What is the standard fixed factory overhead rate per machine hour?
2. What is the denominator activity level that was used to establish the fixed overhead application rate?
3. Prepare a diagram such as the one in Exhibit 15.7, Panel 3, to calculate the following overhead variances for October:
a. Total flexible-budget variance for factory overhead.
b. Fixed overhead production volume variance.
c. Total factory overhead cost variance.
Step by Step Answer:
Cost Management A Strategic Emphasis
ISBN: 978-0077733773
7th edition
Authors: Edward Blocher, David Stout, Paul Juras, Gary Cokins