Six jobs must be processed through machine A and then machine B as shown below. The processing

Question:

Six jobs must be processed through machine A and then machine B as shown below. The processing time for each job is also shown.
Six jobs must be processed through machine A and then

a. Develop a Gantt chart to determine the total time required to process all six jobs. Use the following sequence of jobs: 1, 2, 3, 4, 5, 6.
b. Can you develop a better sequence to reduce the total time required for processing?

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Operations Management in the Supply Chain Decisions and Cases

ISBN: 978-0073525242

6th edition

Authors: Roger Schroeder, M. Johnny Rungtusanatham, Susan Goldstein

Question Posted: