The cost of a plant to produce 1.27 million tonne/y of polyethylene was $540 million. Estimate what

Question:

The cost of a plant to produce 1.27 million tonne/y of polyethylene was $540 million. Estimate what the range of cost estimates would likely have been for a Class 5, a Class 3, and a Class 1 estimate.