Question: A project manager decides to go out for bids on some of the project work that must be done as part of a contract to
A project manager decides to go out for bids on some of the project work that must be done as part of a contract to do a project for another customer. The bids are received and evaluated, and the seller with the lowest bid is selected. The cost of the contract to the project can further be reduced by what action?
a. Illegal methods
b. Procurement leverage
c. Selecting another seller
d. Contract negotiation