In Adaptive Life Cycles (change-driven or Agile methods), ______________. a. the overall scope of the project is
Question:
In Adaptive Life Cycles (change-driven or Agile methods), ______________.
a. the overall scope of the project is fixed, and the time and cost are developed incrementally
b. the overall cost is fixed, and the project scope and schedule are developed iteratively
c. the time and cost are fixed, but the scope is developed iteratively
d. change control is very important