The operating cost of a pulverized coal cyclone furnace is expected to be $80,000 per year. The

Question:

The operating cost of a pulverized coal cyclone furnace is expected to be $80,000 per year. The steam produced will be needed for 6 years—now through year 5. Determine the equivalent annual worth, A, in years 1 through 5 of the operating costs at an interest rate of 10% per year.