5. Assume you have a project with major categories called planning, analysis, design, and testing. Vv'hat level
Question:
5. Assume you have a project with major categories called planning, analysis, design, and testing.
Vv'hat level of the WBS would these items fall under?
a. 0 b.
c. 2
d. 3