5. Which of the following statements is false? a. A resource breakdown structure is a hierarchical structure
Question:
5. Which of the following statements is false?
a. A resource breakdown structure is a hierarchical structure that identWies the project's resources by category and type.
b. Duration and effort are syl"lOnymousterms.
c. A three-point estimate is an estimate that includes an optirristic, most likely, and pessimistic estimate.
d. A Gantt chart is a common tool lor displaying project schedule information.