6. A work breakdown structure, project schedule, and cost estimates are outputs of the ___ process. a.

Question:

6. A work breakdown structure, project schedule, and cost estimates are outputs of the ___ process.

a. initiating

b. planning

c. executing

d. monitoring and controlling

e. closing