Given the following cost expenditures (see Table P6.1) for a small warehouse project (to include direct and
Question:
Given the following cost expenditures (see Table P6.1) for a small warehouse project (to include direct and indirect changes):
A. Calculate the peak financial requirement.
B. Sketch a diagram of the overdraft profile.
C. What would be the impact on the maximum overdraft of giving the contractor a $25,000 mobilization payment? (Show calculation.)
Assumptions:
The markup for this project is 12%.
Retainage is 10% throughout project.
Finance charge is 1.5% per month.
Payments are billed at the end of the month and are received one month later.
All expenses are paid immediately.
Step by Step Answer:
Related Book For
Financial Management And Accounting Fundamentals For Construction
ISBN: 9780470182710
1st Edition
Authors: Daniel W Halpin, Bolivar A Senior
Question Posted: