A firm experienced abnormal scrap and collected data to see which parts were causing the problem with the following results: part A—$5720, part B—$10,250, Part C—$820, Part D—$1130, Part F—$700. Complete the following table listing the errors in descending order of importance. Construct a Pareto diagram.
Part Number Percent Cumulative Percent Total LO.1