The question, How engaged are the stakeholders now, compared to last month?, would most likely be asked
Question:
The question, ‘How engaged are the stakeholders now, compared to last month?’, would most likely be asked in which step of the stakeholder management cycle?
a. Managing Stakeholders
b. Checking for Changes
c. Prioritizing Stakeholders
d. Identifying Stakeholders