Your project has over 25 stakeholders that you actively involve. With such a large group, you decide
Question:
Your project has over 25 stakeholders that you actively involve. With such a large group, you decide to use a formal stakeholder management process to handle these stakeholders. Preparing stakeholder profiles is part of which step in the stakeholder management cycle?
a. Managing Stakeholders
b. Identifying Stakeholders
c. Analyzing Stakeholders
d. Checking for Changes