Your project was just completed and the sponsor rated the project a huge success because it was
Question:
Your project was just completed and the sponsor rated the project a huge success because it was completed on time, on budget and accomplished all the goals outlined in the charter. Half of your team did not show up at the celebration party. Which of these statements would reflect better the full situation?
a. Your project is a success because projects exist for a purpose and if the purpose is accomplished the project is successful
b. Your project is a success because it met the triple constraints of scope, cost and time
c. Your project is a failure because even though the triple constraints were met, the team is unhappy
d. Your project might not be a full success in the eyes of some team members
Step by Step Answer: