1. Which knowledge areas include processes related to closing? A. project scope, schedule, cost, and quality management...

Question:

1. Which knowledge areas include processes related to closing?

A. project scope, schedule, cost, and quality management B. project integration, scope, schedule, cost, and quality management C. project integration and procurement management D. project integration management