44. The work breakdown structure (WBS), the work packages, and the companys accounting system are tied together

Question:

44. The work breakdown structure (WBS), the work packages, and the company’s accounting system are tied together through:

A. The code of accounts B. The overhead rates C. The budgeting system D. The capital budgeting process