45. A program can best be described as: A. A grouping of related activities that lasts two...
Question:
45. A program can best be described as:
A. A grouping of related activities that lasts two years or more B. A collection of projects and other work designed to meet strategic business objectives C. A group of projects managed in a coordinated way to obtain benefits not available from managing them individually D. A product line