63. The major difference between PERT and CPM networks is: A. PERT requires three time estimates whereas
Question:
63. The major difference between PERT and CPM networks is:
A. PERT requires three time estimates whereas CPM uses one time estimate.
B. PERT is used only for construction projects whereas CPM is used solely for R&D.
C. PERT addresses only time whereas CPM also includes costs and resource availability.
D. PERT is measured in days whereas CPM uses weeks or months.