After three months, a six-month project has an earned value of $120K, an actual cost of $130,000,
Question:
After three months, a six-month project has an earned value of
$120K, an actual cost of $130,000, and a planned value of
$100,000. How would you evaluate the project performance?
a. The project is behind schedule and over budget
b. The project is ahead of schedule and under budget
c. The project is behind schedule and under budget
d. The project is ahead of schedule and over budget
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
An Introduction To Project Management Predictive Agile And Hybrid Approaches
ISBN: 9798695713459
7th Edition
Authors: Kathy Schwalbe
Question Posted: