Use the Excel template Gantt Chart to construct an early-start Gantt chart for the computer-system installation project
Question:
Use the Excel template Gantt Chart to construct an early-start Gantt chart for the computer-system installation project described in problem 39. As a project manager, where would you focus your attention, given your analysis?
Data from in Problem 39
A computer-system installation project consists of eight activities. The immediate predecessors and activity times in weeks are shown below:
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Operations And Supply Chain Management
ISBN: 9780357131695
2nd Edition
Authors: David A. Collier, James R. Evans
Question Posted: