A project consists of three tasks: A, B, and C. Task A is known to take five

Question:

A project consists of three tasks: A, B, and C. Task A is known to take five days for sure. Tasks B and C are each dependent on A. B takes five days. C takes seven days with a probability of 0.5 and three days with a probability of 0.5. What is the expected completion time of the project? 

a. 8 days 

b. 10 days 

c. 11 days 

d. 12 days