What is the late start schedule for a project? a. It is the latest start and the
Question:
What is the late start schedule for a project?
a. It is the latest start and the latest completion times of the project activities so that the overall project is still completed on time.
b. It is a schedule that measures the amount of time an ongoing project is late.
c. It is an accelerated schedule in order to get a project with a late start still completed on time.
d. None of these statements is correct.
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Answer rating: 46% (13 reviews)
a It is the latest start an...View the full answer
Answered By
Asim farooq
I have done MS finance and expertise in the field of Accounting, finance, cost accounting, security analysis and portfolio management and management, MS office is at my fingertips, I want my client to take advantage of my practical knowledge. I have been mentoring my client on a freelancer website from last two years, Currently I am working in Telecom company as a financial analyst and before that working as an accountant with Pepsi for one year. I also join a nonprofit organization as a finance assistant to my job duties are making payment to client after tax calculation, I have started my professional career from teaching I was teaching to a master's level student for two years in the evening.
My Expert Service
Financial accounting, Financial management, Cost accounting, Human resource management, Business communication and report writing. Financial accounting : • Journal entries • Financial statements including balance sheet, Profit & Loss account, Cash flow statement • Adjustment entries • Ratio analysis • Accounting concepts • Single entry accounting • Double entry accounting • Bills of exchange • Bank reconciliation statements Cost accounting : • Budgeting • Job order costing • Process costing • Cost of goods sold Financial management : • Capital budgeting • Net Present Value (NPV) • Internal Rate of Return (IRR) • Payback period • Discounted cash flows • Financial analysis • Capital assets pricing model • Simple interest, Compound interest & annuities
4.40+
65+ Reviews
86+ Question Solved
Related Book For
Operations Management
ISBN: 9781260547610
2nd International Edition
Authors: Gerard Cachon, Christian Terwiesch
Question Posted:
Students also viewed these Business questions
-
You have prepared the following schedule for a project in which the key resources is a tractor. There are three tractors available to the project. Activities A and D require one tractor to complete...
-
A competitor of Kozar International, Inc. has begun marketing a new instant- developing film project. Kozar has had a similar product under study in its R&D department but has not yet been able to...
-
The data identified below was listed in a projects latest status report: BCWS = $36,000 BCWP = $30,000 ACWP = $33,000 BAC = $120,000 Original length of the project 10 months Using these data,...
-
Describe how a noninsulating allocation promotes cooperation among managers and encourages mutual monitoring.
-
The plane P1 has the equation 4x - y + 5z = 2. For each of the planes P1 in Exercise 18, determine whether P1 and P are parallel, perpendicular, or neither. In exercise 18 (a) 2x + 3y - z = 1 (b) 4x...
-
16.11 Barley Brindle Limited produces a single product, Product B. One unit of Product B has a prime cost of 6.20, which includes one hour of direct labour @ 6.20, and each unit uses 0.5 hours of...
-
What is the Agile Manifesto? AppendixLO1
-
1. What are the dangers of having a flawed mission statement? 2. How does a flawed statement affect the development of a unit's mission statement and subsequent individual job descriptions and goals?...
-
Use the accounting records below to compute the cost of goods sold. Other Information: $68,000 $65,400 $60,500 $62,300 $66,500
-
Because of increased consumer demand for fuel-efficient, alternative energy automobiles, Global Auto Company is considering investing in a new hybrid crossover vehicle. Development costs each year...
-
A project consists of three tasks: A, B, and C. Task A is known to take five days for sure. Tasks B and C are each dependent on A. B takes five days. C takes seven days with a probability of 0.5 and...
-
Which of the following statements best defines the scope of a project? a. What must be accomplished in order for the project to be completed b. What budget is required to complete the project c. What...
-
If you were CEO of a company, would you spend $10 million per year to put your companys name on a stadium?
-
To create 3 scenarios (positive, neutral and negative) for the development of the restaurant. Include the following important factors in your assessments: border trade as one of the most important...
-
Description of market segment Aged between 34 and 58 Regular commuters Clerical or professional Income over $50K Moderately price-sensitive but may see higher price as an indicator of quality...
-
How has the job of the manager changed over time (since the publication of the Mintzberg article below)? What factors have contributed to shifts in the manager's role? What new roles are managers...
-
a. illustrate the fives modes within which an ethical leader can exercise authority b. Evaluate four factors related to interpersonal dimension that relate to unethical behaviour of leaders c. Assess...
-
Complete the following writing assignment: Analyze the attached 10_pages. Write about them, summarize what you read, and connect it to personal experiences. CHAPTER 15 Sexual Dysfunctions and...
-
Fill in the blanks with an appropriate word, phrase, or symbol(s). In medieval times, people referred to the golden proportion as the ________ proportion.
-
Revol Industries manufactures plastic bottles for the food industry. On average, Revol pays $76 per ton for its plastics. Revol's waste-disposal company has increased its waste-disposal charge to $57...
-
Under what circumstances should a c-chart be used instead of a p-chart?
-
What is the difference between tolerances and control limits?
-
What is the difference between tolerances and control limits?
-
Chapter o Homew ebook 50,000-unit production quantity: $ 227,049 7 70,000-unit production quantity: $ 66,751 d. In addition to mean profit, what other factors should FTC consider in determining a...
-
Diamond makes downhill ski equipment. Assume that comic has offered to produce ski poles for Diamond for $20 per pair Diamond needs 200,000 pairs of poles per period Diamond can only avoid 5150,000...
-
17? Which of the following statement is true Select one: a. All evidence must have the same level of reliability b. All evidence must have the same level of persuasiveness C. All are false d....
Study smarter with the SolutionInn App