A software company hires a new programmer to write the coding sequences for a software project. It is estimated that the new programmer will take 30 hours to write the first coding sequence. Assuming a learning rate of 90%, calculate:

1. The estimated time required to code the 5th coding sequence

2. The total time required for all five coding sequences