Consider the AON graph of a project shown in Figure 19.18. The activity times are 3, 4,

Question:

Consider the AON graph of a project shown in Figure 19.18. 


The activity times are 3, 4, 2, 5, 7, 2, 2, and 3 days for activities A1 through A8, respectively. What is the critical path? 

a. A1 , A2 , A3 , A4 , A8 

b. A1 , A2 , A3 , A6 , A7 , A8 

c. A, A2 , A5 , A7 , A8 

d. None of these options is the critical path.