Consider the following three jobs: Job Alpha requires 2 weeks of work and is due in 4
Question:
Consider the following three jobs: Job Alpha requires 2 weeks of work and is due in 4 weeks. Job Beta requires 3 weeks of work and is due in 5 weeks. Job Carlos requires 1 week of work and is due in 3 weeks. If these jobs are completed in alpha- betical order, how late will job Beta be?