Consider the following three jobs: Job Oscar requires 2 weeks of work and is due in 4
Question:
Consider the following three jobs: Job Oscar requires 2 weeks of work and is due in 4 weeks. Job Lima requires 3 weeks of work and is due in 5 weeks. Job Denver requires 1 week of work and is due in 3 weeks.
a. If these jobs are completed in alphabetical order, what is the tardiness associated with job Oscar?
b. If these jobs are completed in alphabetical order, what would be the makespan of the schedule?
c. If shortest processing time were used to sequence these three jobs, what would be the average flowtime of that sequence?