Suppose for problem 2, you found a new supplier who could guarantee deliveries, allowing you to change

Question:

Suppose for problem 2, you found a new supplier who could guarantee deliveries, allowing you to change project variance to 9 days.

1. Recalculate the probabilities of finishing the project in 50, 70, and 90 days.

2. What is the due date in this circumstance that will yield a 99% probability of completion?

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Operations Management Managing Global Supply Chains

ISBN: 978-1506302935

1st edition

Authors: Ray R. Venkataraman, Jeffrey K. Pinto

Question Posted: