Suppose you are deciding on whether to crash a projects activities and you have the following information:

Question:

Suppose you are deciding on whether to crash a project€™s activities and you have the following information:

Duration Activity Predecessors B 5 2 D 6. 8. E,F 4+ 3.

Normal Crashed Cost Extra Cost Activity (in U.S. dollars) Duration (in U.S. dollars) Duration 5,000 4 weeks 4,000 3 week


1. Construct the project€™s network. What is the project€™s duration? What activities have slack time? What is the critical path?

2. Identify the sequencing of the activities to be crashed in the first four steps. Which critical activities should be crashed first? Why?

3. After four iterations involving crashing project activities, what has the critical path shrunk to?

4. Assume that a project penalty clause kicks in after 19 weeks. The penalty charged is $5,000 per week after 19 weeks. How would this information affect your decision to crash the project?

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Operations Management Managing Global Supply Chains

ISBN: 978-1506302935

1st edition

Authors: Ray R. Venkataraman, Jeffrey K. Pinto

Question Posted: