A project consists of seven activities. The precedence relationships are given in the following table. Time Immediate
Question:
A project consists of seven activities. The precedence relationships are given in the following table.
Time Immediate Activity (days) Predecessors A 32 B 21 C 30 D 45 A E 26 A, B F 28 C G 20 E, F
a. Construct a network for this project.
b. Compute the earliest and the latest starting and finishing times for each activity and identify the critical path.
c. Draw a Gantt chart of the schedule for this project based on earliest starting times.
d. What group of activities will have to be completed by day 60 in order to guarantee that the project will not be delayed?
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Production And Operations Analysis
ISBN: 9781478623069
7th Edition
Authors: Steven Nahmias, Tava Lennon Olsen
Question Posted: