A project consists of seven activities. The precedence relationships are given in the following table. Time Immediate

Question:

A project consists of seven activities. The precedence relationships are given in the following table.

Time Immediate Activity (days) Predecessors A 32 B 21 C 30 D 45 A E 26 A, B F 28 C G 20 E, F

a. Construct a network for this project.

b. Compute the earliest and the latest starting and finishing times for each activity and identify the critical path.

c. Draw a Gantt chart of the schedule for this project based on earliest starting times.

d. What group of activities will have to be completed by day 60 in order to guarantee that the project will not be delayed?

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Production And Operations Analysis

ISBN: 9781478623069

7th Edition

Authors: Steven Nahmias, Tava Lennon Olsen

Question Posted: