Consider Example 10.5 presented in this section in which the two programmers are to develop a commercial
Question:
Consider Example 10.5 presented in this section in which the two programmers are to develop a commercial software package.
a. What is the minimum project time and the total direct cost of completing the project in that time?
b. Suppose that all the activity times are reduced to their minimum values. Explain why the total direct cost obtained in Example 10.5 is different from the cost you obtained in part (a).