Three machines, M1, M2, and M3, are required to complete the project. The requirements for each activity

Question:

Three machines, M1, M2, and M3, are required to complete the project. The requirements for each activity are as follows:

Activity Machines Required A M1, M2 B M1, M3 C M2 D M1, M2 E M2 F M1, M3 G M2, M3 H M1 Determine the minimum time required to complete the project if there is only one machine of each type available. How many weeks are added to the project time when resource requirements are considered?