Beta Inc., has received orders to deliver turbines, for which the product structure tree and delivery schedule

Question:

Beta Inc., has received orders to deliver turbines, for which the product structure tree and delivery schedule are given below. The test and delivery procedure, which is not shown here, takes three weeks.image text in transcribed

Month 1 2 3 4 5 6 Quantity 200 300 400 200 400 500 After four months of the production schedule, the cumulative number of units produced at each process stage is shown in the following table.
Cumulative Production at the End of 4th Month Process Steps Cumulative Production I 1500 II 1300 III 1200 IV 700 V 900 VI 850 VII 700 Develop an LOB chart and evaluate the status of production at each process stage, using the line of balance technique.AppendixLO1