1. ComprehensionGantt charts work as a precedence diagram for the overall project by linking together all activities....
Question:
1. Comprehension—Gantt charts work as a precedence diagram for the overall project by linking together all activities. The Gantt chart is laid out along a horizontal time line so that viewers can quickly identify the current date and see what activities should have been completed, which should be in progress, and which are scheduled for the future. Furthermore, because these activities are linking in the network, it is possible to identify predecessor and successor activities.
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Project Management Achieving Competitive Advantage
ISBN: 9780136057666
5th Edition
Authors: Jeffrey K. Pinto
Question Posted: