For the network shown in Figure Q6.5.1: (a) What are the critical path and the project duration?

Question:

For the network shown in Figure Q6.5.1:

(a) What are the critical path and the project duration?

(b) If the estimated duration for activity ‘C’ is revised to 8 days, will the critical path remain the same as earlier?