When are the resource requirements estimated? a. After the activities have been defined but before the schedule

Question:

When are the resource requirements estimated?

a. After the activities have been defined but before the schedule has been developed

b. After the schedule has been developed but before the activities have been defined

c. As soon as the scope statement is agreed to by the customer

d. After the deliverables are contracted