I just learned the Earned Value formulas and now parts of these formulas have new names. But

Question:

I just learned the Earned Value formulas and now parts of these formulas have new names. But frankly, we don't even do Earned Value calculations in my company. What am I missing?

A. You're not missing anything. No one uses Earned Value anyway.

B. Shhh! Your friends will be embarrassed that you don't use Earned Value.

C. Nothing has changed. Parts of the formulas simply have new names that are a bit easier to understand.

D. Earned Value is the profit left after the cost of supplies is deducted.