These Jobs need to be scheduled on one machine: Job 1 2 3 4 5 6 7 8 9 Processing time in minutes 200 260

These Jobs need to be scheduled on one machine:

Job

1

2

3

4

5

6

7

8

9

Processing time in minutes

200

260

420

180

300

160

90

130

210

a. Process the jobs in their numerical order. Determine the average flow time in hours after each job is completed.

b. Determine the order the jobs would be processed using the SPT rule. Determine the flow time using SPT.

c. Compare your answer with the one you had for problem 2a, then suggest what the better approach is. Explain your answer.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

a Job Processing time in minutes Flow Timein minutes 1 200 200 ... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

OM6 operations supply chain management

Authors: David Alan Collier, James R. Evans

6th edition

1305664795, 978-1305888210, 1305888219, 978-1305664791

More Books

Students also viewed these Accounting questions