These Jobs need to be scheduled on one machine: Job 1 2 3 4 5 6 7 8 9 Processing time in minutes 200 260
These Jobs need to be scheduled on one machine:
Job | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 |
Processing time in minutes | 200 | 260 | 420 | 180 | 300 | 160 | 90 | 130 | 210 |
a. Process the jobs in their numerical order. Determine the average flow time in hours after each job is completed.
b. Determine the order the jobs would be processed using the SPT rule. Determine the flow time using SPT.
c. Compare your answer with the one you had for problem 2a, then suggest what the better approach is. Explain your answer.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
a Job Processing time in minutes Flow Timein minutes 1 200 200 ...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get StartedRecommended Textbook for
OM6 operations supply chain management
Authors: David Alan Collier, James R. Evans
6th edition
1305664795, 978-1305888210, 1305888219, 978-1305664791
Students also viewed these Accounting questions
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
View Answer in SolutionInn App