Question
1. A critical path task is a task with which type of float? A. Total float B. Summed float C. Free float D. Zero float
1. A critical path task is a task with which type of float?
A. Total float
B. Summed float
C. Free float
D. Zero float
2. This is the longest full path on the project. __________ __________.
3. T/F. Free float is the amount of time you can delay the early start of a task without delaying the finish date of the project.
4. Describe how float is calculated.
5. Add this type of time to the project schedule to account for unforeseen circumstances__________ __________.
6. Most human resources are not available 100% of the time for project work. A good rule of thumb is to use the following percentage:
A. 65 - 70
B. 70 - 75
C. 75 - 80
D. 80 - 85
7. This technique attempts to smooth out the resource assignments.
8. T/F. Most scheduling software packages will display schedules in a Gantt Chart view.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started