1. A critical path task is a task with which type of float? A. Total float B. Summed float C. Free float D. Zero float

1. A critical path task is a task with which type of float?

A. Total float

B. Summed float

C. Free float

D. Zero float

2. This is the longest full path on the project. __________ __________.

3. T/F. Free float is the amount of time you can delay the early start of a task without delaying the finish date of the project.

4. Describe how float is calculated.

5. Add this type of time to the project schedule to account for unforeseen circumstances__________ __________.

6. Most human resources are not available 100% of the time for project work. A good rule of thumb is to use the following percentage:

A. 65 - 70

B. 70 - 75

C. 75 - 80

D. 80 - 85

7. This technique attempts to smooth out the resource assignments.

8. T/F. Most scheduling software packages will display schedules in a Gantt Chart view.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Motivated

Authors: For Goodness Sake Network

1st Edition

B0CNMLYFJ3

More Books

Students also viewed these General Management questions

Question

Explain the function and purpose of the Job Level Table.

Answered: 1 week ago