14 Consider the following work breakdown structure: 14 Start Finish Time Estimates (wks) Activity Node Node to tm tp points 23444 12231 ABCDE 11 20
14 Consider the following work breakdown structure: 14 Start Finish Time Estimates (wks) Activity Node Node to tm tp points 23444 12231 ABCDE 11 20 2 5 18 30 42 7 10 23 29 8 13 31 40 43 What is the probability that the critical path for this project will be completed within 52 weeks? Multiple Choice 3466 8277 3108 6554 1554