1a.) In a project activity network, activity F has three immediate predecessors: B, C, and E. The earliest completion times for B, C, and E

1a.) In a project activity network, activity F has three immediate predecessors: B, C, and E. The earliest completion times for B, C, and E are 6, 18, and 11 days. What is the earliest start time for F?

1b.) A firm made 90,315 units in 2009, with an average of 90 employees.In 2010, the production was 110,348 units, with an average of 96 employees.What is the percentage increase in productivity from 2009 to 2010?(Note: if there is a decrease, the increase is negative;provide two digits to the right of the decimal point)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Quantitative Methods For Business

Authors: David Anderson, Dennis Sweeney, Thomas Williams, Jeffrey Cam

11th Edition

978-0324651812, 324651813, 978-0324651751

More Books

Students also viewed these General Management questions