Question
1 Approved Answer
1a.) In a project activity network, activity F has three immediate predecessors: B, C, and E. The earliest completion times for B, C, and E
1a.) In a project activity network, activity F has three immediate predecessors: B, C, and E. The earliest completion times for B, C, and E are 6, 18, and 11 days. What is the earliest start time for F?
1b.) A firm made 90,315 units in 2009, with an average of 90 employees.In 2010, the production was 110,348 units, with an average of 96 employees.What is the percentage increase in productivity from 2009 to 2010?(Note: if there is a decrease, the increase is negative;provide two digits to the right of the decimal point)
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started