2 . 3 . Use RVA to evaluate the status of progress of the Project at the end of week 6 by doing the following:

2.3. Use RVA to evaluate the status of progress of the Project at the end
of week 6 by doing the following:
a) Create a table that includes all the activities with the three costs (PV.
AC,EV) up to week 6 only. Each column of the table will represent a
week.
b) Calculate the costs and the cumulative costs at the end of each week.
c) Calculate the Cost and Schedule variances only for week. 6, as well as
the CPI and SPI indices at the end of week 6.
d) Estimate how much it will cost to complete the project according to
the current performance level (total cost of the project).
e) Estimate how long it will take to complete this project according to
the current performance level. Give the answer in days.
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Linear Optimization And Duality A Modern Exposition

Authors: Craig A. Tovey

1st Edition

1439887462, 9781439887462

More Books

Students also viewed these General Management questions

Question

How much did the company purchase from that supplier?

Answered: 1 week ago