2 . 3 . Use RVA to evaluate the status of progress of the Project at the end of week 6 by doing the following:
Use RVA to evaluate the status of progress of the Project at the end
of week by doing the following:
a Create a table that includes all the activities with the three costs PV
up to week only. Each column of the table will represent a
week.
b Calculate the costs and the cumulative costs at the end of each week.
c Calculate the Cost and Schedule variances only for week. as well as
the CPI and SPI indices at the end of week
d Estimate how much it will cost to complete the project according to
the current performance level total cost of the project
e Estimate how long it will take to complete this project according to
the current performance level. Give the answer in days.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started