6.7. International Door Slammers has an order to deliver 500 door slammers on day 130. Draw up a backward schedule under the following conditions. Only
6.7. International Door Slammers has an order to deliver 500 door slammers on day 130. Draw up a backward schedule under the following conditions.
Only one machine is assigned to each operation.
Schedule one 8-hour shift per day for 5 days per week.
All parts are to move in one lot of 500 pieces.
Allow 8 hours between operations for queue and move times.